How to source custom bedding from China: RFQ to shipment
Sourcing custom bedding from China typically runs 8–12 weeks from first enquiry to FOB shipment for a first order: about 1–2 weeks for specification and quotation, 7 days for sampling, 2–3 weeks for fabric and print preparation, 30–45 days for bulk production, then packing and ocean freight. Repeat orders with approved samples on file move faster. Document decisions at each gate to avoid costly changes after approval.
Last updated: 2026-11-14 · Published by TRX Home Textile
| Gate | Activity | Indicative time |
|---|---|---|
| 1 | Specification and RFQ | 2–5 days |
| 2 | Quotation, MOQ and terms | 1–2 days |
| 3 | Artwork / strike-off and sample development | About 7 days |
| 4 | Sample approval, compliance documents | 3–7 days |
| 5 | Fabric preparation, dyeing and bulk production | 30–45 days |
| 6 | In-line and finished-goods QC | Included in stage 5 |
| 7 | Packing, carton marks, documentation | 3–5 days |
| 8 | Ocean freight from Ningbo / Shanghai | Depends on destination |
1. Write an RFQ that can actually be quoted
A vague enquiry produces a vague price. Include the product category, target quantity, fabric type or GSM, filling weight where relevant, size chart, number of colourways, Pantone or physical colour references, print or tufting artwork, set composition, packaging format, destination port, trade term, required certificates and target price. State which of these are fixed and which are flexible.
Also say who you are selling to. A program for a European discounter, a US hotel group and an Amazon private-label seller will need different compliance documents, packaging and inspection regimes. Telling the factory up front prevents a quote that looks cheap but fails your retailer's inbound requirements.
2. Verify the factory, not just the price
Check that the legal entity quoting you is the entity that will produce the goods, and that its address matches the audit and certificate documents. Request certificate PDFs and verify numbers, scope and validity dates with the issuer. For licensed character programs, confirm the FAMA covers your specific category and territory. Ask whether the supplier manages weaving, dyeing, cutting, sewing, QC and packing in-house or subcontracts — it directly affects lead-time control and colour consistency across a coordinated range.
Where the order justifies it, commission a third-party audit or pre-shipment inspection. Build it into the schedule at RFQ stage rather than adding it at the end.
3. Use the sample stage to freeze decisions
The sample is where you lock hand feel, shade tolerance, GSM, fill weight, dimensions, stitching and trims, care-label wording and packaging dielines. Ask for the packaging to be sampled with the product, not afterwards — a beautiful comforter in the wrong carton or with a non-compliant care label still fails at inbound.
Keep a signed approved sample and a written specification sheet. Any change after approval affects cost and schedule. A factory with in-house processes can usually turn samples around in about 7 days; use that week for decisions rather than treating the sample as a formality.
4. Production, inspection and shipping
Confirm the trade term (EXW or FOB), who handles export documentation, carton marks, barcodes and the packing list before production begins. For printed programs, agree the shade tolerance and how bulk will be checked against the approved strike-off. Inspection should happen at fabric, in-line and finished-goods stages, not only at the end.
Finally, plan backwards from your shelf date: 30–45 days bulk production, sampling and artwork, ocean freight, customs clearance and the retailer's inbound window. Peak seasons compress capacity across the entire supply chain; a confirmed delivery date early in the process is worth more than a slightly lower unit price.
Frequently asked questions
How long does a first custom bedding order take?
For a first order, plan roughly 8–12 weeks from approved artwork to FOB shipment, including sampling, 30–45 days bulk production and ocean freight. Repeat orders with approved samples on file are faster.
What is a realistic MOQ for a new private-label brand?
Bedding sets commonly start at 500 sets per design and towels or kids textiles at 1,000 pieces. A smaller trial order can often be negotiated for a first collaboration.
Which trade terms should I ask for?
FOB Ningbo or FOB Shanghai is a common starting point. Confirm in writing who handles export documentation, carton marks and the packing list.
Which certificates should I request?
At minimum BSCI or an equivalent social audit and OEKO-TEX Standard 100 for product safety. Add GOTS or GRS documentation for organic or recycled claims, and FAMA for licensed character programs.
How do I avoid colour mismatches on bulk?
Agree Pantone TCX or physical references and a shade tolerance before production, approve a washed strike-off, and confirm in-process shade control with the factory.
Can I mix sizes and colourways in one container?
Mixing sizes within one design is usually straightforward. Multiple colourways may each carry their own minimum. Ask the factory to quote both structures.
Request a quote
Send your product, quantity, target price and destination port. Our export team replies within 24 hours on working days with an indicative price, MOQ and sample lead time.
English and Chinese support · Samples in about 7 days · Certificates available on request
Request a quote